ICT OFFICER II – PROJECT MANAGEMENT PRACTICAL EXAMINATION- MOCK

Position: ICT Officer II
Subject: Project Management
Examination Type: Practical/Competency-Based Assessment
Duration: 3 Hours
Total Marks: 100

Instructions

  1. Attempt all tasks.
  2. Use Microsoft Excel, Microsoft Project, or equivalent project-management software where appropriate.
  3. Clearly show all calculations.
  4. Assume that all monetary values are in TZS.
  5. Save your work using the format:
    ICT_OfficerII_Project_Management_[YourName]
  6. Submit all required files at the end of the examination.

 

PRACTICAL SCENARIO

You have been appointed as an ICT Officer II in an organization implementing an Electronic Document Management System (EDMS).

The project will digitize paper-based records and introduce an electronic document management system for improved document storage, retrieval, security, and workflow.

The project has the following major objectives:S

  • Digitize existing paper records.
  • Implement an electronic document management system.
  • Configure user access controls.
  • Train staff.
  • Improve document retrieval and security.
  • Deploy the system across selected departments.

 

TASK 1: PROJECT INITIATION – 10 MARKS

Prepare a Project Charter containing:

  1. Project title
  2. Project justification
  3. Project goal
  4. At least five SMART objectives
  5. Project sponsor
  6. Project manager
  7. Key stakeholders
  8. Major deliverables
  9. Project assumptions
  10. Project constraints
  11. Success criteria

Expected Output

Submit the Project Charter as a Word or PDF document.

 

TASK 2: WORK BREAKDOWN STRUCTURE – 10 MARKS

Develop a Work Breakdown Structure (WBS) for the EDMS project.

Your WBS should include at least the following phases:

  1. Project initiation
  2. Project planning
  3. Requirements analysis
  4. System design
  5. Procurement
  6. System configuration
  7. Data/document migration
  8. Testing
  9. User training
  10. Deployment
  11. Monitoring and support
  12. Project closure

Break each phase into appropriate work packages and activities.

Expected Output

Submit:

  • Hierarchical WBS
  • WBS numbering
  • Work packages
  • Deliverables

 

TASK 3: PROJECT SCHEDULING AND GANTT CHART – 15 MARKS

Create a project schedule using Microsoft Project or Excel.

Use the following activities:

ID

Activity

Duration

Predecessor

1

Project initiation

3 days

2

Project planning

5 days

1

3

Requirements gathering

7 days

2

4

System analysis

5 days

3

5

System design

7 days

4

6

Procurement

10 days

2

7

System configuration

10 days

5,6

8

Data preparation

8 days

4

9

Data migration

10 days

7,8

10

System testing

7 days

9

11

User acceptance testing

5 days

10

12

User training

5 days

11

13

System deployment

3 days

11,12

14

Post-implementation support

10 days

13

15

Project closure

3 days

14

Requirements

Produce:

  • Start and finish dates
  • Duration
  • Dependencies
  • Gantt chart
  • Milestones
  • Critical activities

 

TASK 4: CRITICAL PATH METHOD – 10 MARKS

Using the schedule in Task 3:

  1. Calculate the Critical Path.
  2. Calculate the earliest start (ES).
  3. Calculate the earliest finish (EF).
  4. Calculate the latest start (LS).
  5. Calculate the latest finish (LF).
  6. Calculate the float for each major activity.
  7. State the total project duration.

Use:

Float = LS − ES

or

Float = LF − EF

Expected Output

Prepare a table similar to:

Activity

Duration

ES

EF

LS

LF

Float

Critical?

Project initiation

3

Project planning

5

Requirements

7

...

...

 

TASK 5: RESOURCE MANAGEMENT – 10 MARKS

Prepare a resource allocation plan for the project.

Consider the following resources:

Resource

Role

Project Manager

Project coordination

ICT Officer II

Technical coordination

Business Analyst

Requirements

System Analyst

System analysis

Software Developer

Configuration/customization

Database Administrator

Database management

Network Administrator

Network infrastructure

Cybersecurity Officer

Security

Records Officer

Records management

Trainer

User training

Support Technician

Technical support

For each resource, identify:

  • Assigned activities
  • Estimated effort
  • Responsibility
  • Availability
  • Possible resource constraints

Identify at least two resource conflicts and recommend solutions.

 

TASK 6: PROJECT RISK MANAGEMENT – 10 MARKS

Create a Project Risk Register containing at least 10 risks.

Consider risks such as:

  • Budget shortage
  • Delayed procurement
  • Resistance to change
  • Data loss
  • Cybersecurity attack
  • Poor-quality scanned documents
  • System downtime
  • Inadequate user training
  • Vendor failure
  • Requirements changes

Use the following format:

Risk

Probability

Impact

Risk Score

Mitigation

Contingency

Owner

Data loss

High

High

Regular backup

Restore backup

DBA

Cyberattack

Medium

High

Security controls

Incident response

Security Officer

Calculate:

Risk Score = Probability × Impact

Use a scale of:

  • 1 = Very Low
  • 2 = Low
  • 3 = Medium
  • 4 = High
  • 5 = Very High

 

TASK 7: PROJECT BUDGET – 10 MARKS

Prepare a project budget using the following estimates:

Cost Item

Estimated Cost (TZS)

Software

18,000,000

Servers

25,000,000

Network equipment

12,000,000

Scanners

8,000,000

Data migration

10,000,000

Training

7,000,000

Consultancy

15,000,000

Maintenance

5,000,000

Assume a 10% contingency.

Calculate:

  1. Direct project cost
  2. Contingency amount
  3. Total project budget

Then prepare the budget in Excel and create a suitable chart.

 

TASK 8: EARNED VALUE MANAGEMENT – 10 MARKS

After implementation has started, the following information is provided:

  • Planned Value (PV) = TZS 45,000,000
  • Earned Value (EV) = TZS 40,000,000
  • Actual Cost (AC) = TZS 50,000,000

Calculate:

A. Cost Variance

CV = EV − AC

B. Schedule Variance

SV = EV − PV

C. Cost Performance Index

CPI = EV ÷ AC

D. Schedule Performance Index

SPI = EV ÷ PV

Interpret the results and state whether the project is:

  • Over or under budget
  • Ahead or behind schedule

As an ICT Officer II, recommend three corrective actions.

 

TASK 9: CHANGE MANAGEMENT – 5 MARKS

During implementation, management requests the addition of a mobile application to the EDMS.

Prepare a Change Request containing:

  1. Change description
  2. Reason for change
  3. Business justification
  4. Impact on scope
  5. Impact on schedule
  6. Impact on cost
  7. Technical impact
  8. Risks
  9. Recommendation
  10. Approval decision

Explain how you would process the change using formal change control.

 

TASK 10: PROJECT STATUS REPORT – 10 MARKS

Prepare a professional Project Status Report for senior management.

The report should contain:

Project Information

  • Project name
  • Project manager
  • Reporting period
  • Overall project status

Performance

Report on:

  • Scope
  • Schedule
  • Cost
  • Quality
  • Risks
  • Issues
  • Resources

Management Information

Include:

  • Completed activities
  • Activities in progress
  • Delayed activities
  • Major risks
  • Corrective actions
  • Decisions required from management
  • Planned activities for the next reporting period

Use RAG status:

🟢 Green – On track
🟡 Amber – Requires attention
🔴 Red – Critical/problem

 

FINAL SUBMISSION REQUIREMENTS

The candidate should submit the following:

No.

Deliverable

Marks

1

Project Charter

10

2

WBS

10

3

Project Schedule & Gantt Chart

15

4

Critical Path Analysis

10

5

Resource Management Plan

10

6

Risk Register

10

7

Project Budget

10

8

Earned Value Analysis

10

9

Change Request

5

10

Project Status Report

10

TOTAL

100

Key Competencies Being Assessed

This practical examination tests whether an ICT Officer II can practically demonstrate:

  • Project initiation
  • Project planning
  • WBS development
  • Project scheduling
  • Gantt chart preparation
  • Critical Path Method (CPM)
  • Resource allocation
  • Risk management
  • Budget management
  • Earned Value Management (EVM)
  • Change control
  • Project monitoring and reporting
  • ICT project governance
  • Stakeholder communication
  • Problem-solving and corrective action planning


NB: "ANYTHING CAN HAPPEN"


 