OFFICER II – PROJECT MANAGEMENT PRACTICAL EXAMINATION- MOCK
Position:
ICT Officer II
Subject: Project Management
Examination Type: Practical/Competency-Based Assessment
Duration: 3 Hours
Total Marks: 100
Instructions
- Attempt all tasks.
- Use Microsoft Excel, Microsoft
Project, or equivalent project-management software where appropriate.
- Clearly show all calculations.
- Assume that all monetary values are
in TZS.
- Save your work using the format:
ICT_OfficerII_Project_Management_[YourName] - Submit all required files at the end
of the examination.
PRACTICAL
SCENARIO
You
have been appointed as an ICT Officer II in an organization implementing
an Electronic Document Management System (EDMS).
The
project will digitize paper-based records and introduce an electronic document
management system for improved document storage, retrieval, security, and
workflow.
The
project has the following major objectives:S
- Digitize existing paper records.
- Implement an electronic document
management system.
- Configure user access controls.
- Train staff.
- Improve document retrieval and
security.
- Deploy the system across selected
departments.
TASK
1: PROJECT INITIATION – 10 MARKS
Prepare
a Project Charter containing:
- Project title
- Project justification
- Project goal
- At least five SMART objectives
- Project sponsor
- Project manager
- Key stakeholders
- Major deliverables
- Project assumptions
- Project constraints
- Success criteria
Expected
Output
Submit
the Project Charter as a Word or PDF document.
TASK
2: WORK BREAKDOWN STRUCTURE – 10 MARKS
Develop
a Work Breakdown Structure (WBS) for the EDMS project.
Your
WBS should include at least the following phases:
- Project initiation
- Project planning
- Requirements analysis
- System design
- Procurement
- System configuration
- Data/document migration
- Testing
- User training
- Deployment
- Monitoring and support
- Project closure
Break
each phase into appropriate work packages and activities.
Expected
Output
Submit:
- Hierarchical WBS
- WBS numbering
- Work packages
- Deliverables
TASK
3: PROJECT SCHEDULING AND GANTT CHART – 15 MARKS
Create
a project schedule using Microsoft Project or Excel.
Use
the following activities:
|
ID |
Activity |
Duration |
Predecessor |
|
1 |
Project
initiation |
3
days |
— |
|
2 |
Project
planning |
5
days |
1 |
|
3 |
Requirements
gathering |
7
days |
2 |
|
4 |
System
analysis |
5
days |
3 |
|
5 |
System
design |
7
days |
4 |
|
6 |
Procurement |
10
days |
2 |
|
7 |
System
configuration |
10
days |
5,6 |
|
8 |
Data
preparation |
8
days |
4 |
|
9 |
Data
migration |
10
days |
7,8 |
|
10 |
System
testing |
7
days |
9 |
|
11 |
User
acceptance testing |
5
days |
10 |
|
12 |
User
training |
5
days |
11 |
|
13 |
System
deployment |
3
days |
11,12 |
|
14 |
Post-implementation
support |
10
days |
13 |
|
15 |
Project
closure |
3
days |
14 |
Requirements
Produce:
- Start and finish dates
- Duration
- Dependencies
- Gantt chart
- Milestones
- Critical activities
TASK
4: CRITICAL PATH METHOD – 10 MARKS
Using
the schedule in Task 3:
- Calculate the Critical Path.
- Calculate the earliest start (ES).
- Calculate the earliest finish (EF).
- Calculate the latest start (LS).
- Calculate the latest finish (LF).
- Calculate the float for each major
activity.
- State the total project duration.
Use:
Float
= LS − ES
or
Float
= LF − EF
Expected
Output
Prepare
a table similar to:
|
Activity |
Duration |
ES |
EF |
LS |
LF |
Float |
Critical? |
|
Project
initiation |
3 |
||||||
|
Project
planning |
5 |
||||||
|
Requirements |
7 |
||||||
|
... |
... |
TASK
5: RESOURCE MANAGEMENT – 10 MARKS
Prepare
a resource allocation plan for the project.
Consider
the following resources:
|
Resource |
Role |
|
Project
Manager |
Project
coordination |
|
ICT
Officer II |
Technical
coordination |
|
Business
Analyst |
Requirements |
|
System
Analyst |
System
analysis |
|
Software
Developer |
Configuration/customization |
|
Database
Administrator |
Database
management |
|
Network
Administrator |
Network
infrastructure |
|
Cybersecurity
Officer |
Security |
|
Records
Officer |
Records
management |
|
Trainer |
User
training |
|
Support
Technician |
Technical
support |
For
each resource, identify:
- Assigned activities
- Estimated effort
- Responsibility
- Availability
- Possible resource constraints
Identify
at least two resource conflicts and recommend solutions.
TASK
6: PROJECT RISK MANAGEMENT – 10 MARKS
Create
a Project Risk Register containing at least 10 risks.
Consider
risks such as:
- Budget shortage
- Delayed procurement
- Resistance to change
- Data loss
- Cybersecurity attack
- Poor-quality scanned documents
- System downtime
- Inadequate user training
- Vendor failure
- Requirements changes
Use
the following format:
|
Risk |
Probability |
Impact |
Risk
Score |
Mitigation |
Contingency |
Owner |
|
Data
loss |
High |
High |
Regular
backup |
Restore
backup |
DBA |
|
|
Cyberattack |
Medium |
High |
Security
controls |
Incident
response |
Security
Officer |
Calculate:
Risk
Score = Probability × Impact
Use
a scale of:
- 1 = Very Low
- 2 = Low
- 3 = Medium
- 4 = High
- 5 = Very High
TASK
7: PROJECT BUDGET – 10 MARKS
Prepare
a project budget using the following estimates:
|
Cost
Item |
Estimated
Cost (TZS) |
|
Software |
18,000,000 |
|
Servers |
25,000,000 |
|
Network
equipment |
12,000,000 |
|
Scanners |
8,000,000 |
|
Data
migration |
10,000,000 |
|
Training |
7,000,000 |
|
Consultancy |
15,000,000 |
|
Maintenance |
5,000,000 |
Assume
a 10% contingency.
Calculate:
- Direct project cost
- Contingency amount
- Total project budget
Then
prepare the budget in Excel and create a suitable chart.
TASK
8: EARNED VALUE MANAGEMENT – 10 MARKS
After
implementation has started, the following information is provided:
- Planned Value (PV) = TZS
45,000,000
- Earned Value (EV) = TZS 40,000,000
- Actual Cost (AC) = TZS 50,000,000
Calculate:
A.
Cost Variance
CV
= EV − AC
B.
Schedule Variance
SV
= EV − PV
C.
Cost Performance Index
CPI
= EV ÷ AC
D.
Schedule Performance Index
SPI
= EV ÷ PV
Interpret
the results and state whether the project is:
- Over or under budget
- Ahead or behind schedule
As
an ICT Officer II, recommend three corrective actions.
TASK
9: CHANGE MANAGEMENT – 5 MARKS
During
implementation, management requests the addition of a mobile application
to the EDMS.
Prepare
a Change Request containing:
- Change description
- Reason for change
- Business justification
- Impact on scope
- Impact on schedule
- Impact on cost
- Technical impact
- Risks
- Recommendation
- Approval decision
Explain
how you would process the change using formal change control.
TASK
10: PROJECT STATUS REPORT – 10 MARKS
Prepare
a professional Project Status Report for senior management.
The
report should contain:
Project
Information
- Project name
- Project manager
- Reporting period
- Overall project status
Performance
Report
on:
- Scope
- Schedule
- Cost
- Quality
- Risks
- Issues
- Resources
Management
Information
Include:
- Completed activities
- Activities in progress
- Delayed activities
- Major risks
- Corrective actions
- Decisions required from management
- Planned activities for the next
reporting period
Use
RAG status:
🟢 Green – On track
🟡 Amber – Requires
attention
🔴 Red –
Critical/problem
FINAL
SUBMISSION REQUIREMENTS
The
candidate should submit the following:
|
No. |
Deliverable |
Marks |
|
1 |
Project
Charter |
10 |
|
2 |
WBS |
10 |
|
3 |
Project
Schedule & Gantt Chart |
15 |
|
4 |
Critical
Path Analysis |
10 |
|
5 |
Resource
Management Plan |
10 |
|
6 |
Risk
Register |
10 |
|
7 |
Project
Budget |
10 |
|
8 |
Earned
Value Analysis |
10 |
|
9 |
Change
Request |
5 |
|
10 |
Project
Status Report |
10 |
|
TOTAL |
100 |
Key
Competencies Being Assessed
This
practical examination tests whether an ICT Officer II can practically
demonstrate:
- Project initiation
- Project planning
- WBS development
- Project scheduling
- Gantt chart preparation
- Critical Path Method (CPM)
- Resource allocation
- Risk management
- Budget management
- Earned Value Management (EVM)
- Change control
- Project monitoring and reporting
- ICT project governance
- Stakeholder communication
- Problem-solving and corrective action
planning